Our environmental activities at Avenza
At Avenza, we are committed to the environmental remediation of the site in lots, that will enable the progressive redevelopment of areas.
Our commitment for the environmental remediation and the recovery of the Avenza industrial site
Avenza at a glance
Avenza past and present
Site history
Eni Rewind begins the site remediation process
Eni Rewind takes charge of the permanent safety measures interventions and begins the remediation process of the site.
Trasfer to Enichem
The site is transferred to Enichem (now Eni Rewind).
Permanent closure of the plants
Following a major incident in March 1984, the activities, already partially halted, are suspended and the plant closed permanently in June of the same year.
Conferment by law to Eni
The Avenza site is conferred by law to Eni, first under ANIC and then ANIC Agricoltura, for the production of fertilisers and herbicides.
Trasfer to the SIR group
Site management is transferred to the SIR group.
Establishment of the Avenza site
Rumianca basic chemicals and fertiliser plants are built.
Our activities at Avenza
Avenza Former Rumianca
In 2004, we began emergency groundwater safety measures with the construction of a hydraulic barrier and a groundwater treatment plant (GTP). Between 2004 and 2005, we carried out emergency soil safety measures, including covering and waterproofing contaminated areas and draining and collecting rainwater. Furthermore, in 2017, we completed the demolition of obsolete industrial facilities. With the approval of the groundwater remediation project, we strengthened the hydraulic barrier, currently consisting of 33 pumping wells and the existing GTP, increasing the treatment capacity to 200 m³/h. At the site, we are conducting trials for a bioremediation technology that promotes the biodegradation of contaminants (chlorinated solvents) directly in the groundwater. Regarding soil remediation, the project involves excavation and disposal interventions in subsequent lots to ensure the progressive availability of the areas for new developments. The remediation activities were started in compliance with the procedures stated in the operational protocol for the execution and testing of excavations approved by the Tuscany Region and other authorities in 2020 and revised in 2022.
Avenza Former Italiana Coke
In 2024, the company completed the soil characterisation plan and in 2025 submitted a risk analysis for unsaturated soil, which was approved in June 2026 and is currently awaiting the Tuscany Region’s decision. In 2023 the company submitted a groundwater remediation project which is currently undergoing preliminary investigation.
The Massa and Carrara Site of National Priority
Status of the environmental process
The groundwater and soil remediation projects in Avenza (Rumianca) were approved in 2016 and 2018 respectively. The procedure involving the former Italiana Coke site is currently undergoing preliminary investigations.